Key – Red highlight indicates on satellite image of bays general location of proposed buoys.  Total moorings indicate amount expected to be installed with the timescale breaking down  the schedule for the installation until total number is reached.

Prickly Bay  

Total moorings: Planned installation end of 2025 – 55

Planned installation end of 2026 – 75

Mt. Hartman Bay 

Total moorings: Planned installation end of 2025 – 40

Planned installation end of 2026 – 75

Hog Island 

Total moorings: Planned installation end of 2025 – 25 (Mangrove Hurricane) Planned installation end of 2026 – 50

Planned installation end of 2027 – 75

Central/ Lower Woburn Bay 

Total moorings: Planned installation end of 2025 – 45

Planned installation end of 2026 – 65

Planned installation end of 2027 – 85

Upper Woburn Bay 

Total moorings: Planned installation end of 2025 – 25

Planned installation end of 2026 – 35

Planned installation end of 2027 – 45

Morne Rouge Beach 

Total moorings: Planned installation end of 2025 – 5 Day Moorings Planned installation end of 2026 – 20 Overnight Moorings.